Interactive Project Management Demonstration

Project Cost Forecasting

Compare alternative Estimate at Completion forecasts, understand the assumptions behind each method, calculate Estimate to Complete and Variance at Completion, and select a forecast that reflects the expected conditions for the remaining work.

Demonstration at a glance
Level Intermediate
Typical duration 10–15 minutes
Learning format Guided forecast comparison
Best for Project managers, cost engineers and controls professionals
Demonstration overview

Forecast the Final Cost by Making the Assumption Explicit.

Project cost forecasting is not a single-formula exercise. Different Estimate at Completion methods answer different questions because each one assumes something different about the remaining work. This demonstration compares four common forecasting approaches and shows how the choice of assumption changes the forecast.

  • Review BAC, PV, EV, AC, and a bottom-up ETC estimate.
  • Calculate CPI and SPI as the performance basis for forecasting.
  • Forecast EAC when remaining work is expected to perform at the original budgeted rate.
  • Forecast EAC when current CPI is expected to continue.
  • Forecast EAC when both cost and schedule inefficiency are expected to influence remaining work.
  • Build a bottom-up EAC from a revised ETC estimate.
  • Compare ETC and VAC across all forecasting methods.
  • Select the method that best matches the expected remaining-work conditions.
Guided Demonstration

Project Cost Forecasting — Step by Step

Complete each locked stage before the next unlocks. Every reveal changes the forecast dashboard so each method, result, and assumption remains visible beside the learning step.

Learning stages
Foundation Stage 1 of 8

Review the Forecast Source Data

Current instruction
Interactive Forecast Dashboard

EAC Scenarios, ETC, VAC and Assumptions

Forecast source data are revealed one value at a time.

100%
Budget-rate forecast CPI forecast CPI × SPI forecast Bottom-up forecast

Focus Mode moves you to the Guided Demonstration, then hides the rest of the page while keeping the current learning stage and forecast dashboard visible together. Zoom affects only the visual pane.

Forecast Comparison — EAC, ETC, VAC and Assumption
Forecast status: Review the source data before calculating performance and forecasts.
Supporting Forecast Table

Cost Forecast Methods

Forecast rows appear progressively with the guided sequence. The assumption behind each method is shown with its result.

Forecast / Measure Formula Result Assumption / Interpretation
Experiment Mode

Change the Performance Data and Forecast Assumption

Experiment Mode is isolated from the guided example. Change the project status values and bottom-up ETC, then select a forecast method to see the resulting EAC, ETC, VAC, and interpretation.

EAC $126,000
ETC $54,000
VAC −$6,000
CPI / SPI 0.92 / 0.88
Check Your Understanding

Quick Knowledge Check

Choose an answer, then check it.
Project Cost Forecasting Quick Reference

Forecast Methods and Assumptions

Method Formula Use When
Budgeted-rate EAC EAC = AC + (BAC − EV) Past variance is treated as atypical and remaining work is expected to perform at the original budgeted rate.
CPI-based EAC EAC = BAC / CPI Current cost efficiency is expected to continue.
CPI × SPI EAC EAC = AC + (BAC − EV) / (CPI × SPI) Both cost and schedule inefficiency are expected to influence remaining work.
Bottom-up EAC EAC = AC + Bottom-up ETC The remaining work has been re-estimated in detail and the new ETC is considered more credible than a performance-index extrapolation.
ETC ETC = EAC − AC Forecast additional cost required from the status date to completion.
VAC VAC = BAC − EAC Expected final budget variance; negative indicates a forecast overrun.
Forecast-selection rule: the formula is not the decision. First determine what management believes about the remaining work, then select the forecasting method whose assumption matches that expectation. Document the assumption alongside the forecast.
Past Problem Atypical → AC + Remaining Budget
CPI Continues → BAC / CPI
New Detailed ETC → AC + Bottom-Up ETC