Resource Levelling
Build an initial precedence-based schedule, load a constrained resource, identify an overallocation, apply a priority rule, level the conflict, and observe the effect on activity dates and project duration.
See How Resource Constraints Change the Schedule.
Resource levelling adjusts activity start and finish dates when resource demand exceeds available capacity. This demonstration begins with a valid precedence schedule, then introduces a single constrained Planner resource so you can see exactly where the schedule becomes infeasible and how levelling resolves the conflict.
- Review six activities, durations, predecessors, and resource assignments.
- Build the initial precedence-based schedule one activity at a time.
- Load the Planner resource and identify the period of overallocation.
- Apply a transparent priority rule to decide which competing activity moves.
- Shift the lower-priority activity and propagate the effect to its successors.
- Compare the original and levelled schedules, including the change in project duration.
Resource Levelling — Step by Step
Complete each stage before the next stage unlocks. The schedule and resource profile update beside the learning panel so you can see each decision immediately.
Review the Activity and Resource Data
Activity Timeline and Planner Capacity
The initial schedule is built activity by activity.
Focus Mode moves you to the Guided Demonstration, then hides the rest of the page while keeping the current stage and schedule visual together. Zoom affects only the timeline.
Initial and Levelled Dates
The table reveals dates progressively. Levelled dates appear only after the conflict has been resolved and successor dates have been recalculated.
| Activity | Predecessor(s) | Duration | Resource | Initial Start | Initial Finish | Levelled Start | Levelled Finish | Shift |
|---|
Change Capacity and the Priority Rule
Explore how the same precedence schedule behaves under different Planner capacities and levelling priorities.
Quick Knowledge Check
Core Rules and Concepts
| Concept | Rule | Practical Meaning |
|---|---|---|
| Overallocation | Resource demand > available capacity | The precedence schedule is not resource-feasible. |
| Resource Levelling | Adjust activity dates to remove resource overallocations | Project duration or critical path may change. |
| Priority Rule | Determines which competing activity keeps its date | Different rules can produce different levelled schedules. |
| Propagation | Successor dates must be recalculated after a shift | One resource decision can affect downstream work. |
| Resource Smoothing | Adjust within available float | Does not change the critical path or project completion date. |
| Resource-Constrained Schedule | Precedence logic + actual resource availability | Represents a schedule that can realistically be executed. |